You hardly ever hear the words ahead of schedule on big projects like this one, but here it is!
Ahead of schedule,
An update on Utilities work for the IN VALENTINE projects:
Midlands Contracting, Inc. will complete Sanitary Sewer work in the current removal areas. Water Mains are in...
An update for Utilities work for the IN VALENTINE projects:
Haven’t found a tunnel yet, but looking. 😊
Midlands Contracting, Inc. continues construction of Storm Sewer, Sanitary Sewer, and Water Mains. All Sanitary Sewer is in place for the block of 3rd & Main to 4th & Main....
Utilities work continues for the IN VALENTINE projects:
See attached notice for Water Service Shut Off Notice.
Please be advised that water service will be turned off on Tuesday, April 26th, 2022 from 9 am to 1 pm to lower the water main piping. The areas
affected will be...
Planning for this week:
Midlands Contracting, Inc. plans to complete Storm Sewer work at 3rd & Main this week and will continue preparations to open the 3rd Street crossing. A second crew will begin placement of the Sanitary Sewer and Manholes working North from 3rd Street...
Here is the current update from the Nebraska Dept. of Roads. The first portion, tearing out a section of Main St. went quickly. Hopefully it will continue to be done in as timely a manner as is possible.
The current controlling operation for construction of this project is now...
The first week of construction of the IN VALENTINE project is complete. A lot of visible progress.
The construction will switch to Utilities Work this week as the removal work is complete. A lot of work to be done with the results buried, visual progress will seem to be slower. Some...
The following is an update from NE Department of Transportation:
Placement of Temporary Traffic Control
Expect Signs, barrels, and temporary traffic lights to be in place.
Traffic will be routed to Cherry Street Detour.
Measures have been taken to allow access to...
Good morning, Valentine!
As of this weekend, traffic control at the various intersections was removed and pedestrian traffic previously affected on Cherry Street sidewalks has been restored. After a month and a half of road construction, vehicular traffic has been reinstated as normal, all...
As we reach the middle of the week, there are multiple updates to be shared regarding the Main Street Project. It is our pleasure to announce work is nearing completion for Phase 1.
The fuel tank discovered at 4th and Main Street has been removed and repair of an existing copper water line...
As Moonlight Madness weekend kicks off, there is updated information regarding Phase 1 construction. Concrete resurfacing has concluded at the Highway 20 and Cherry Street intersection. At this time however, this route is still unaccessible for use. Traffic will be reinstated depending on...