Here is the current update from the Nebraska Dept. of Roads. The first portion, tearing out a section of Main St. went quickly. Hopefully it will continue to be done in as timely a manner as is possible.
The current controlling operation for construction of this project is now Utilities Work – sanitary sewer. Midlands Contracting, Inc. is planning to mobilize (2) crews onto the IN VALENTINE project with one working on sanitary sewer and the other crew working on storm sewer placement. Expect mobilization to begin with 10+ semi loads of equipment and materials to be delivered to the work area. Preparations are being made to begin work April 4th.
What to expect this week:
Effectiveness of Temporary Traffic Control
Utilities
Sidewalk Requirements and Pedestrian Accommodations
The following guidelines are to help business understand planned sidewalk construction adjacent to entry ways.
Current planning has left more than the required 4’ wide sidewalk in place when possible. This sidewalk next to the buildings will stay in place until roadway and curb are built.
Take a look at the "Explore Valentine & Cherry County" Travel Guide. Explore all that Valentine & Cherry County have to offer!
To see all of the upcoming events in the Valentine area, take a look at our calendar.